Activities in Estimate the Project

8 activities · 1 phase

# Name Abbrev. Guidance Dependencies Actions
Elaboration 8
1 Assess Estimation Readiness EST-1 Purpose Determine what inputs are available, choose the appropriate estimation level (Level 1 SWAG vs. …
2 Calibrate Reference Stories EST-2 Purpose Define concrete reference stories at each T-shirt size, assign K-token baselines (tokens per story …
3 Size Scenarios (Level 1 SWAG) EST-3 Purpose Assign a T-shirt size (XS → XL) to every BDD scenario using the reference …
4 Assess Risk Multipliers EST-4 Purpose Two separate multiplier assessments are performed here: Section A — Internal (ECF/TCF): Rate Environmental …
5 Produce Rough Estimates + AFP EST-5 Purpose Produce two parallel outputs from the Level 1 sizing: Internal token budget — SP …
6 Decompose Work Packages (Level 2) EST-6 Purpose At Level 1 (EST-03) you sized features by T-shirt. That was good enough for …
7 Run Monte Carlo Simulation EST-7 Purpose Execute Monte Carlo simulation (10,000 iterations, triangular distributions) over the scenario-level PERT triplets to …
8 Sprint Close & Rebaseline EST-8 Purpose At the end of each sprint, collect actual token consumption, compute Velocity Factor (VF …